----- Renewable Energy & Electrical Infrastructure

Bright Source Energy (BSE) South Africa (Pty) Ltd
Near Upington, Northern Cape, South Africa
Start Date: 31 August 2021
End Date: 31 October 2023


Project Details


Project Managers:
Bright Source Energy (BSE)
 
Ziva Shavit
Engineer:
Bright Source Energy (BSE)
 
Yossi Azancot
Contract Manager:
Chris de Waal
Construction Manager:
CJ van der Westhuizen
Date of Award:
03  September 2021
Completion Date:
14 March 2024
Contract Period
31 Months
Description:
Assembly and installation of approximately 40 000 heliostats arranged in an array around the Power Tower and design & construction of Mirror Assembly Facility (MAF) Building.
The Works Include:
  • MAF Building Construction
  • Crane installation
  • Steel structures
  • Cable installation, termination, and testing
  • Weather station and CCTV installation, termination, and testing
  • Approximately 40 000 micro piles and concreting
  • Approximately 40 000 heliostat assembled and installed