Huawei Technologies Zambia LTD
Zambia
Start Date: 19 November 2019
End Date: 19 May 2020
PROJECT MANAGERS: | Danie MaraisCell : 071 608 4088Email : danie.m@raubex.com |
ENGINEER: | N/A |
RESIDENT ENGINEER: | N/A |
CONTRACT MANAGER: | Patrick FrayneCell : +260 965 723906Email : Patrick.f@raubex.com |
SITE AGENT: | Schalk Van NiekerkCell : 079 241 8163Email : Schalk.v@raubex.com |
CONTRACT INFORMATION: | DATE OF AWARD | REVISED |
DATE OF AWARD | 25 November 2015 | |
COMPLETION DATE | 30 June 2016 | |
VALUE (INCL VAT) | R104 million | |
CONTRACT PERIOD | 6 months | |
SCOPE OF WORKS:
DESCRIPTION: Supply and Install telecom backbone network | |
THE WORKS INCLUDE: Civil works to trench, lay and backfill long haul routes using mainly direct laying methodologies | |
QUANTITY INDICATORS (AS BILLED IN TENDER DOCUMENT): | |
CLEARING AND GRUBBING SITE | 1022km |
TRENCH EXCAVATION | 1022km |
MASS EARTHWORKS | |
LAYERWORKS | |
EXCAVATION TO ACCESS,SLABS AND DRAINAGE | |
DOUBLE SEAL ASPHALT SURFACINGMASS CONCRETE (BASES AND DRAINAGE)CONDUITS | 1022km |
CABLE LAYING | 1022km |
Supply and Install telecom backbone network