Explore our portfolio

Our core focus is on building personal relationships with strategic partners in executing turn-key projects.

Image for Juwi - Copperton PV Solar Farm (86MW)
Juwi - Copperton PV Solar Farm (86MW)

Juwi Renewable Energies (Pty) Ltd

Copperton Northern Cape, South Africa

Start Date: 05 October 2024

End Date: 05 February 2025


Image for Elwan - Copperton Wind Energy Facility (102MW)
Elwan - Copperton Wind Energy Facility (102MW)

Renewable Energy & Electrical Infrastructure

Copperton Wind Farm (RF) Proprietary Limited (Elwan)

Copperton, Northern Cape, South Africa

Start Date: 21 August 2018

End Date: 18 January 2022


Image for Scatec - Linde Solar Panel Farm (40MW)
Scatec - Linde Solar Panel Farm (40MW)

Renewable Energy & Electrical Infrastructure

Scatec Solar SA 163 (Pty) Ltd

Near Hanover, Northern Cape, South Africa

Start Date: 12 September 2018

End Date: 12 November 2018


Image for Transnet - Repair, Sandblast and Paint of Glen Steel Bridge
Transnet - Repair, Sandblast and Paint of Glen Steel Bridge

Transnet Freight Rail

Glen outside Bloemfontien, Free State, South Africa

Start Date: 12 December 2017

End Date: 15 September 2019


Image for Liciastar - Kat1 CSP: Electrical Works
Liciastar - Kat1 CSP: Electrical Works

Renewable Energy & Electrical Infrastructure

Liciastar (Pty) Ltd

Kat1 CSP, Kathu, Northern Cape, South Africa

Start Date: 01 November 2016

End Date: 26 February 2018


Image for BSE - Redstone CSP 100 MW Thermal Power Plant
BSE - Redstone CSP 100 MW Thermal Power Plant

Renewable Energy & Electrical Infrastructure

Bright Source Energy (BSE) South Africa (Pty) Ltd

Near Upington, Northern Cape, South Africa

Start Date: 31 August 2021

End Date: 31 October 2023


Image for Alcatel Lucent - Camps Bay Fibre to Home
Alcatel Lucent - Camps Bay Fibre to Home

Telecommunication & Special Projects

Alcatel Lucent (Nokia)

Camps Bay, Cape Town, Western Cape, South Africa

Start Date: 12 December 2017

End Date: 25 December 2019


Image for Independent Development Trust - Reinstatement of the Kwazulu-Natal foot and Mouth disease control Barrier (Middle B Portion)
Independent Development Trust - Reinstatement of the Kwazulu-Natal foot and Mouth disease control Barrier (Middle B Portion)

Independent Development Trust

Kwazulu-Natal, South Africa

Start Date: 19 July 2019

End Date: 19 December 2019


Image for Huawei - Supply and Install telecom backbone fibre network
Huawei - Supply and Install telecom backbone fibre network

Telecommunication & Special Projects

Huawei Technologies Zambia LTD

Zambia

Start Date: 19 November 2019

End Date: 19 May 2020


Image for Eskom - Upgrading of Jordan Substation In Bethlehem
Eskom - Upgrading of Jordan Substation In Bethlehem

Telecommunication & Special Projects

Eskom

Bethlehem, Free State, South Africa

Start Date: 12 December 2017

End Date: 11 November 2019