Back to Projects
----- Telecommunication & Special Projects

Alcatel Lucent (Nokia)
Camps Bay, Cape Town, Western Cape, South Africa
Start Date: 12 December 2017
End Date: 25 December 2019


Project Details


PROJECT MANAGERS:                                                    Eugene Gouws
 

ENGINEER:                                                                        N/A
 
RESIDENT ENGINEER:                                                     N/A
 

CONTRACT MANAGER:                                                Danie Marais
 

SITE AGENT:                                                                   Tjaard Booyens

 

CONTRACT INFORMATION:

DATE OF AWARD

REVISED

DATE OF AWARD

20 November 2015


COMPLETION DATE

31 November 2016


VALUE (INCL VAT)
                    R15 million

CONTRACT PERIOD
                       1 year

 

SCOPE OF WORKS:

DESCRIPTION:   FTTX for Alcatel Lucent

THE WORKS INCLUDE:
 
Install Fibre to the home for Telkom at Camps bay Cape town. Contract is to connect 960 houses with fibre for high speed internet.
 
  •  

QUANTITY INDICATORS (AS BILLED IN TENDER DOCUMENT):


TRENCH EXCAVATION  =34 km

Construct manholes = 56

Hauling of ducts  = 130 km

Install aerial cable = 85  km

Splicing test = 2314 splices
Cable Floating = 67 km

                                                   


FTTX for Alcatel Lucent