Department of Roads and Public Works
The rehabilitation of DR2963 and MR 739 from National Route 7 (N7) to Hondeklipbaai – Phase 2 – Klipfontein (km12.0) to MR 739 (km19.8)
Start Date: 12 December 2017
End Date: 10 December 2019
PROJECT MANAGERS: | Cornel Strydom 28 Tibbie Visser Estoire Bloemfontein Tel : 051 011 1593 |
ENGINEER: | Mr M Myburgh 17A Keerom Street Springbok, 8240 Tel : 027 712 9990 Fax : 027 712 9991 |
RESIDENT ENGINEER: | Mr D Roode Tel: 082 802 5979 |
| |
CONTRACT MANAGER: | Cornel Strydom 28 Tibbie Visser Estiore Bloemfontein Tel : 051 011 1593 |
SITE AGENT: | Christo Taljaard Tel: 082 895 8385 Email: Christo.t@raubex.com |
CONTRACT INFORMATION: | DATE OF AWARD | REVISED |
DATE OF AWARD | 20 January 2016 | |
COMPLETION DATE | 10 March 2017 | |
VALUE (INCL VAT) | R89 925 742.17 | |
CONTRACT PERIOD | 13 Months |
SCOPE OF WORKS:
DESCRIPTION: | |
The rehabilitation of DR2963 and MR 739 from National Route 7 (N7) to Hondeklipbaai – Phase 2 – Klipfontein (km12.0) to MR 739 (km19.8) | |
THE WORKS INCLUDE: | |
Building a new road between Klipfontein and the Hondeklipbaai road (km12 -19.8), including a new junction on MR739 | |
QUANTITY INDICATORS (AS BILLED IN TENDER DOCUMENT): | |
Accommodation of Traffic Overhaul Clearing and Grubbing Dayworks Drains Prefabricated Culverts Concrete chutes Asphalt and Concrete berms Borrow Materials Crushing and screening Mass earthworks Pavement Layers of gravel material Prime Bituminous single seal with slurry Stone Pitching Gabions Guardrails Fencing Road signs Roadmarkings Finishing the road and road reserve |
The rehabilitation of DR2963 and MR 739 from National Route 7 (N7) to Hondeklipbaai – Phase 2 – Klipfontein (km12.0) to MR 739 (km19.8) |