Pennyville Zamimphilo Relocations (Pty) Ltd / Calgro M3 Holdings
Vista Park, Bloemfontein, Free State, South Africa
Start Date: 03 May 2022
End Date: 04 July 2023
Client Representative: | Deon Steyn |
Raubex Infra Project Manager: | Nikki Carnicelli |
Raubex Infra Construction Manager: | Siphosihle Madliwa |
Engineer: | Bigen Africa |
| Andre Wesson |
Resident Engineer: | - |
Project Value (ExIncl. Vat) | R102 898 223,65 |
Scope of Works: |
Nature Of Works: Construction of civil Engineering Services for 204 erf stands and link roads for Vista Park Extension 257, 262, 263 |
The Works Include: |
UPVC water mains, reticulated in street reserves consisting of 3 717km of 110mmØ – 200mmØ pipes Internal Ext 257: -110mmØ of 1 030m -160mmØ of 725m -200mmØ of 285m Internal Ext 262: -110mmØ of 835m Internal Ext 263: -110mmØ of 842m Installation of 110mm UPVC ducts for house connections in road crossings Connection to existing link water line UPVC street front sewers consisting of 4 433km of 160mmØ -200mmØ pipes with precast concrete manholes. Internal Ext 257: -160mmØ of 1 920m Internal Ext 262: -160mmØ of 835m Internal Ext 263: -160mmØ of 842m Link: -160mmØ of 625m -200mmØ of 211m Link and Internal Roads and Stormwater infrastructure: Internal Ext 257: -13m road reserves (2.5m roadway width) of 420m -16m road reserves (3.5m roadway width) of 1 433m -16m road reserves (3.7m roadway width) of 240m -450mmØ stormwater pipes of 1 071m -525mmØ stormwater pipes of 143m Internal Ext 262: -13m road reserves (2.5m roadway width) of 230m -16m road reserves (3.7m roadway width) of 605m -450mmØ stormwater pipes of 111m -600mmØ stormwater pipes of 50m -750mmØ stormwater pipes of 10m -825mmØ stormwater pipes of 81m Internal Ext 263: -13m road reserves (2.5 roadway width) of 481m -16m road reserves (3.7m roadway width) of 361m -450mmØ stormwater pipes of 120m Link: -20m road reserves (3.7m roadway width) of 1 130m -450mmØ stormwater pipes of 523m -525mmØ stormwater pipes of 10m -600mmØ stormwater pipes of 53m -900mmØ stormwater pipes of 40m Kerb- and drop inlet stormwater structures and junction boxes Related layer-works for road and stormwater channels Installation of cable ducts for electrical reticulation road crossings |