Rand Water
Rietvlei nature reserve to Mamelodi, Gauteng, South Africa
Start Date: 02 March 2020
End Date: 30 August 2021
Rand Water Project Manager: | Virosha Singh |
Raubex Infra / Enza JV Contract Manager: | Daniele Carnicelli |
Raubex Infra Construction Manager: | Nikki Carnicelli |
Rand Water Engineer(s): | John Cato |
| Sandisile Ngubane |
Project Value (Incl. Vat) | R136 513 665.79 |
Scope of Works: |
Nature Of Works: Construction of a 19 138m long by 1 500m diameter steel pipe for the H46 pipelines from Rietvlei nature reserve to Mamelodi, including earth works, pipe laying and associated works (H46B) |
Quantity Indicators | |
Clearing and Grubbing Site | 93 5003m² |
Trench Excavations (Various Depths) | 36 465m3 |
Steel Pipelaying – including welding and making good of external and internal linings | 4675m |
Installation of Junction Boxes & Field Inlets | 28 210m3 |
Backfilling | 11656m3 |
2.1m diam Pipe Jackings – 9 No. Total | 210m |