Rand Water
Rietvlei nature reserve to Mamelodi, Gauteng, South Africa
Start Date: 02 March 2020
End Date: 30 August 2021
Client Representative: | Virosha Singh | |
Raubex Infra / Enza JV Contract Manager | Daniele Carnicelli | |
Raubex Infra Construction Manager: | Nikki Carnicelli | |
Engineer (Company): | Rand Water | |
| Engineer (RE): | John Cato |
| Engineer (RE): | Sandisile Ngubane |
Scope of Works: | |
Description: Construction of a 1,5m diameter steel pipe for the H46 pipelines from Rietvlei nature reserve to Mamelodi, including earth works, pipe laying and associated works (H46B) | |
The works include: | |
1. | Clearing and grubbing site |
2. | Excavation (various depths) and back-filling of trenches |
3. | Steel pipe laying, including welding and external and internal linings re-in-statement |
4. | Construction of valve and scour chambers |
5. | 2.1m diameter pipe jacking |
6. | Connect to existing line |