City of Cape Town Metropolitan Municipality
Milnerton Rural, Cape Town
Start Date: 21 December 2028
End Date: 21 August 2028
Client Representative: | Sameeh Johaadien |
Raubex Infra Operations Director: | Andries Swart |
Raubex Infra Projects Director: | Nikki Carnicelli |
Raubex Infra Construction Manager: | Mel van Aswegen |
Engineer (Company): | Bigen Africa |
Engineer: | Dr. Gideon de Villiers |
Scope of Works: | |
Description: Design and build of mechanical and electrical works for the upgrade and expansion of Potsdam Wastewater Treatment Plant | |
The works include Installation of: | |
1. | Eskom bulk supply works, 11Kv Feeder Panels and associated medium voltage cable & associated works) |
2. | Primary & secondary Mv switchgear incomer substation & battery tripping units and batteries. |
3. | Primary & secondary Mv substation earthing & protection schemes |
4. | 2000KVA generators |
5. | 1600KVA and 2500KVA Power Transformers |
6. | Multicore cables, earth wires & associated works |
7. | 800VA ring main units & miniature substations |
8. | Site lighting |
9. | Perimeter security fence, CCTV hardware & software, indoor fixed camera, indoor PTZ Cameras, Outdoor Fixed Cameras, and outdoor PTZ cameras |
10. | Complete access control system incl. all hardware and software |