African Clean Energy Development (ACED)
Between Richmond and Murraysburg, Western Cape, South Africa
Start Date: 28 October 2026
End Date: 28 May 2027
Client Representative: | Sam Cook | |
Raubex Infra Operations Director: | Chris de Waal | |
Raubex Infra Projects Director: | Jaco De Jager | |
Raubex Infra Lead Construction Manager: | Jaco Fick | |
Owners | Engineer (Company): | Zutari |
| Engineer: | James Larmuth |
Civil: | Engineer (Company): | BVI |
| Engineer: | Dirk van der Merwe |
Electrical | Engineer (Company): | Thabile |
| Engineer: | Abrie Deacon |
Scope of Works: | |
Description: Northern cluster windfarms: the civil, electrical and balance of plant EPC for 3 windfarms namely Ishwati, Khangela and Umsinde | |
The works on each windfarm includes: | |
1. | O & M buildings & guard houses |
2. | Roads, hardstands, buffer yards & associated storm water |
3. | Cable trenches |
4. | Substations |
5. | Overhead lines |
6. | Electrical works including all installation, testing and commissioning |
7. | Wind turbine foundations |